CASE STUDY | COMPLETED

Sanand Heavy Automobile Stamping & Assembly Plant

Apex Auto Infrastructure Ltd — Sanand Industrial Estate, Ahmedabad, Gujarat

3,20,000 Sq.Ft.Built-up Area
3400 MTStructural Steel
36m Column-FreeClear Span
16m HeightClear Height
PROJECT OVERVIEW

High-Performance Structural Engineering

A heavy industrial manufacturing complex featuring four 36m-wide parallel production bays equipped with tandem 50-tonne and 30-tonne overhead EOT cranes for automotive stamping and robotic body-in-white assembly.

The Requirement

Extreme structural rigidity with strict deflection limits (L/1000 for crane runways) under heavy cyclic dynamic braking and acceleration loads, along with high-volume ventilation to dissipate heat from welding lines.

Engineering Challenge

Engineering heavy stepped columns (up to 1800mm depth) and surge trusses to carry dynamic crane loads without transmitting lateral vibrations into delicate robotic laser-welding cells on adjacent mezzanine floors.

OUR SOLUTION

Engineered Structural Steel Strategy

Designed composite box-column assemblies and heavy built-up crane runway girders with continuous high-strength friction-grip (HSFG) Grade 10.9 bolting. 1200mm continuous aerodynamic ridge ventilators and motorized intake louvers were integrated to achieve 14 air changes per hour.

Design Details

  • Dynamic harmonic vibration analysis in STAAD.Pro to prevent structural resonance with operating press equipment
  • Custom crane surge truss geometry absorbing lateral trolley braking forces
  • Heavy mezzanine deck carrying 2,500 kg/m² auxiliary stamping tooling loads

Fabrication

  • Heavy built-up plate girders up to 40mm thickness with 100% radiographic weld testing
  • Precision CNC line-boring of crane girder connection holes for exact rail alignment
  • Zinc silicate high-durability primer for enhanced corrosion resistance

Erection

  • Tandem heavy crane lifts utilizing 120-tonne hydraulic telescopic cranes
  • Sub-millimeter optical theodolite rail alignment across 250m long crane runway tracks
  • Rapid turnkey erection executed within 18 weeks

The precision of Yatee's heavy fabrication is world-class. Our 50-tonne overhead cranes rolled across the 250-meter runway tracks with zero vibration from day one.

Rameshwar Patel

VP – Projects & Plant Engineering, Apex Auto Infrastructure Ltd

Project Data Sheet

Structural Metrics

Client:Apex Auto Infrastructure Ltd
Location:Sanand Industrial Estate, Ahmedabad
Industry Vertical:Industrial & Manufacturing
Building Typology:Heavy Industrial Factory with 50T Crane Girders
Built-Up Area:3,20,000 Sq. Ft.
Steel Tonnage:3400 MT
Clear Height:16 Meters
Clear Span:36 Meters
Status / Year:Completed (2024)
SIMILAR REQUIREMENT?

Build a Similar High-Performance Facility

Our estimation engineers will provide a preliminary 3D model and steel tonnage calculation for your site location.

Request Similar Project Estimate
Instant WhatsApp Enquiry